(make_predictions, arx_forecaster, epix_slide) don't work together quite correctly:
make_predictions takes a given ref_time_value (= target date), fetches the data $as_of that target date, but then doesn't pass that target date through to make_predictions; instead, make_predictions assumes that the test_time_value is the latest time_value with data available, which is rarely the case: we typically work off of data with some nonzero latency (or maybe, off of some point forecasts with negative latency). So we end up with forecasts for ref_time_values + ahead - minimum_latency_among_signals, but labeled as forecasts for ref_time_values + ahead.
epix_slide might need updated to pass along the ref time value if it doesn't allow that already.