Changed the manual time estimate to reflect machine down time during the day period. The actual beam time used by the commissioning was closer to 1.5 shift total
1 parent 1da2218 commit 1c6a920

File tree

1 file changed

+1
-1
lines changed

1 file changed

+1
-1
lines changed

docs/logbook/LHC/2025_lhc.md

Lines changed: 1 addition & 1 deletion
Original file line numberDiff line numberDiff line change
@@ -38,7 +38,7 @@ The tables below can be sorted by clicking next to the column headers.
3838
| 2025-06-22 04:00 | 2025-06-22 13:00 | 1.1HN | MD15146 | Rematched IR7 optics | [Shift Start](2025-06-22, 1081, 4322198){.logbook-link} / [Summary](2025-06-22, 1081, 4322924){.logbook-link} ([OP][op_rematched_ir7]{.cern_login target=_blank}) |
3939
| 2025-06-22 15:40 | 2025-06-22 20:40 | 0.5H | MD14963 | MO detuning | [Shift Start](2025-06-22, 1081, 4322659){.logbook-link} / [Summary](2025-06-22, 1081, 4322924){.logbook-link} |
4040
| 2025-06-28 08:30 | 2025-06-28 12:00 | 0.3H | Commissioning | RDT vs phase knob | [Shift Start](2025-06-28, 1081, 4327972){.logbook-link} / [Summary](2025-06-28, 1081, 4328352){.logbook-link} ([OP][op_rdt_vs_phase_knob]{.cern_login target=_blank}) |
41-
| 2025-06-28 12:00 | 2025-06-29 05:00 | 1.5H 1HN | Commissioning | OO Commissioning | [Shift Start](2025-06-28, 1081, 4328097){.logbook-link} / [Summary](2025-06-29, 1081, 4328684){.logbook-link} ([OP][op_oo_commissioning]{.cern_login target=_blank}) |
41+
| 2025-06-28 12:00 | 2025-06-29 05:00 | 0.5H 1HN | Commissioning | OO Commissioning | [Shift Start](2025-06-28, 1081, 4328097){.logbook-link} / [Summary](2025-06-29, 1081, 4328684){.logbook-link} ([OP][op_oo_commissioning]{.cern_login target=_blank}) |